The Process Cooling System Assessment - Linear Low-density Polyethylene Film Cooling


Introduction

Controlled cooling is an essential part of manufacturing polyethylene stretch film. The process starts with granulated polyethylene raw product with very low strength, and develops thin, clear, strong film used in a variety of applications.  It does this by melting, extrusion, “casting” and winding.  See Figure 1 for a typical system diagram. “Casting” is forming and cooling at the same time. The extruded polymer is stretched and cooled on large, chrome-plated rollers with cooling water flowing inside. Thinner film is for manual use, like wrapping around food products. Thicker, stronger product is made for machine use, like automatically wrapping pallets of concrete bags.

Typical stretch film cooling systems include at least one chiller, since designers anticipate that some products might require coolant at a temperature lower than is achievable with an evaporative cooler. They also can include recirculation at each cooling roll. A typical plant has multiple cooling rolls per line and multiple lines, and change product on those lines. That requires independently adjustable coolant loops.

 

Manufacturing Linear Low-density Polyethylene (LLDPE) Film

Plant ABC manufactures linear low-density polyethylene (LLDPE) film used to unitize packaging.  Two lines are run constantly.  Two 140-ton chillers are run all year.  They cool glycol solution from 53 to 49 degrees, which is delivered to the plant via insulated piping.  There are two lines with three cooling zones each, with typical control temperatures of 75 to 108 degrees F.  Temperatures are maintained at each zone via a recirculation pumping system, very energy-intensive.  See Figure 4 for an overall view and Figure 5 for a typical zone.  Processes are described in more detail in this article.  The process cooling system consumes about 182 kW average, about $90,000/yr, or 19% of facility energy use (about 1,500,000 kWh/yr out of 8,000,000).  Savings of about 67% of that can be gained by optimization (12% of total facility -  about 1,000,000 kWh/yr).

In this case, we are recommending an evaporative cooler sized large enough to cool the entire facility when the outside wet-bulb temperature is low enough, and controls to shift between the existing chillers and the evaporative cooler.  This is called “tower-free cooling”, or “economizer cooling”.  At this site, which is a fairly dry location, that freezes in the winter, that would be 75% of the year.  For plants in warmer and more humid environments, the economics will not be as good.  We are also recommending running the recirculation pumps for each zone at lower speed.

Table 1 is a summary of preliminary estimates of costs and benefits for the energy efficiency measures evaluated for this proposed project. Incentives may be available for the measures.  If both of the measures are implemented at one time, and the predicted savings are gained, an investment of about $158,000 will result in savings of about $54,000/yr and less than a 3 yr payback.  This is an attractive investment.

Table 1: Project Economics
 UTILITY RATE SCHEDULE:   XYZ  $8.000 /KW-MO
$0.05000 /KWH 
    
EEM NO. DESCRIPTION EEM LIFE
EXPECTANCY (YRS)
PEAK POWER
SAVINGS (KW)
DEMAND
REDUCTION (KW)
ANNUAL ELECTRIC
SAVINGS (KWH/YR)
ANNUAL ELECTRIC
SAVINGS ($/YR)
INSTALLED COST
($)
PAYBACK
(YRS)
EEM1 Tower Free Cooling & Controls 15 0 0 494,050 $24,703 $139,150 5.6
EEM2 VFDs on Recirculation Pumps 15 62 31 524,881 $29,220 $19,250 0.7
   TOTAL  62  31  1,018,931  $53,923  $154.400  2.9

 

Glycol for the Stretch Film Production Process

Plant ABC operates three shifts Monday to Friday, and keeps the two extruders running all the time except for full plant shut downs and brief product changes. Process systems at the site include extruders, process cooling, pumping, material transport, trim collection, and compressed air. Aside from the production and warehouse areas, the facility includes an office area and warehouse. Lighting and HVAC are not addressed in this Process Cooling Energy Audit.

The plant has been operating at full capacity since startup, and plans on increasing capacity as soon as they can justify the cost of a third extruder. A typical stretch film production process is shown in simplified form in Figure 1. The overall process cooling system is described in Figures 2 and 4. The chillers are providing 49 degrees all year long, even though the primary cooling process doesn’t require less than 75 degrees. Chillers are multi-stage and fairly efficient. Controls are up to date, except that both units are always running. This isn’t particularly inefficient. It just requires more maintenance than necessary, since one chiller can handle the load. Chiller pumps deliver glycol from the warm sump to the chillers, using VFD control. Process pumps deliver coolant from the cool sump to the plant, also with VFD control, set at 18 psig.

A typical “zone” for cooling one roll is shown in Figure 5. The recirculation system bleeds in just enough chiller water to maintain the desired roll outlet temperature. A small amount of coolant comes and goes to the chiller, controlled by a control valve, while most of the flow recirculates through the cooling roll. Excessive pressure differential on the recirculation pumps (and excess power consumption) occurs because the pump is developing more flow than required. They are oversized and are balanced against the system resistance of the cooling roll. This excess recirculation flow results in a temperature differential of only 1.0 degree F across the cooling roll. This low delta T is not adding any value to the process control. Doubling it to 2.0 degrees by running the pumps at about half speed would not even be noticed by the process. Temperature control would still occur by the mixing valves.

Figure 1.  Typical Stretch Film System Diagram

Figure 1.  Typical Stretch Film System Diagram

 

Figure 2.  Typical Cooling Roll

Figure 2.  Typical Cooling Roll

 

Figure 3.  Typical Recirculation Pumping System

Figure 3.  Typical Recirculation Pumping System

 

Existing Equipment

Process Cooling

  • Chiller No 1:  Trane Series R 140 ton, with two compressors, 118 RLA/each.  It uses R134A refrigerant.  This chiller is likely capable of  about 0.8 to 1.2 kW/ton efficiency, depending on load and set point.  However, when we saw it, the load was low because two chillers were being run when only one could have handled the load. 
  • Chiller No 2:  Trane Series R 140 ton, with two compressors, 122 RLA/each.  It uses R22 refrigerant, and will have to be phased out soon due to unavailability of refrigerant.  This chiller is likely capable of about 0.8 to 1.2 kW/ton efficiency, depending on load and set point.  However, when we saw it, the load was low because two chillers were being run when only one could have handled the load. 
  • The average total chiller load is about 82 kW.
  • Piping to process appears to be adequately sized.  We did not investigate in detail if there is throttling at the loads.
  • Cool and warm storage tanks, about 1,500 gallons/each.  Warm glycol solution is pumped from the chiller tank through the chillers and to the process tank by the chiller pumps.  Then, process pumps pump the cool glycol solution from the cool process tank to the system.  Then it returns to the chiller tank.  The chiller cools the chiller glycol loop from 53 to 48 deg F, which is pumped directly to the process.  We estimate that the average heat load is about 51 tons on average.

Chiller and Process Pumping

  • (3) 15 hp centrifugal process pumps (one off, two on VFDs.) Plant ABC’s installed power metering indicated 12 kW and 13 kW load.
  • (2) 15 hp centrifugal process pumps.

Recirculation Pumping

  • Line 1 recirculation system:
    • (1) 30hp pump for primary chill roll.  Control valve at the inlet takes 52F coolant from chilled water supply (CWS) and mixes with recirculated coolant.  Pump discharge is about 85 psig.  Coolant is discharged to chilled water return (CWR.)
    • (1) 10 hp pump for secondary chill roll, similar to the 30 hp.
    • Some pumps are dead-headed.
  • Line 2 recirculation system:
    • (1) 40hp pump for primary chill roll, similar to Line 1.
    • (2) 10 hp pump for secondary chill rolls, similar to Line 1.
    • Some pumps are dead-headed.

Proposed Improvements

See Figures 4 and 5 for recommended improvements.  The recommended project includes the following components:

  • EEM 1: Process Cooling – Tower Free Cooling and Controls.  This measure addresses the process cooling system, not pumping.  It includes the following:
    • New approx. 140 ton closed loop evaporative cooler.
    • Controls to run newer chiller only when cooling tower can’t achieve coolant temperature, usually warm months.  Run at about 65 deg F coolant temperature.
    • Integration of new cooler into piping.  Some design is needed.
    • Two small chillers for the two extruders, in case they need cooler temperatures than the evaporative cooler can provide.  Run at about 52 deg F coolant temperature.
  • EEM 2: VFDs on Recirculation Pumps. This measure consists of the following:
    • (1) 40 hp & (1) 30 hp VFD for recirculation pumps
    • Differential pressure transmitters
    • Reprogram existing PLC to control pump speed and recirculation valve for required pressure differential and controlled temperature.

The energy required to cool using the “free” heat sink provided by nature, the condensing (or “wet bulb”) temperature is dramatic.  For the ¾ of the year that the evaporative cooler can handle the load, the energy requirement is less than 10% of the chiller power at the same heat load.  The recirculation pumps can be run at about half speed most of the time, requiring only about 15% power.  Additional benefits to the proposed improvements include reduced chiller maintenance and improved process control. 

Figures 4 and 5

Implementation Cost Estimate

Total implementation cost of these measures is estimated to be between $140,000 and $160,000, depending on customer preference in measure selection. Estimated costs are shown in the tables below. 

TABLE 2: PRELIMINARY IMPLEMENTATION COST ESTIMATES
EEM1: TOWER FREE COOLING & CONTROLS
ITEM DESCRIPTION PRICE EA QTY QTY PRICE SOURCE
1 Fluid Cooler $70,000 1 $70,000 Vendor ABC quote
2 Dedicated Fluid Cooler Pump $1,500 1 $1,500 CEC Estimate
3 Dedicated Small Chiller $10,000 2 $20,000 Vendor ABC estimate
4 Controller $20,000 1 $20,000 Vendor ABC estimate
5 Fluid Cooler & Chiller Installation $15,000 1 $15,000 CEC Estimate
Contingency 10% $12,650  
Total EEM1 $139,150  
EEM2: VFDS ON RECIRCULATION PUMPS
ITEM DESCRIPTION PRICE EA QTY QTY PRICE SOURCE
1 40hp VFD $5,000 1 $5,000 CEC Estimate
2 30hp VFD $4,000 1 $4,000 CEC Estimate
3 Pressure transmitters $500 2 $1,000 CEC Estimate
4 Installation $3,000 2 $6,000 CEC Estimate
5 Startup/calibrations $1,500 1 $1,500 CEC Estimate
Contingency 10% $1,750 Estimate
Total EEM2 $19,250  

 

Estimate of Baseline Energy Consumption and Energy Savings

Tables 3-4 below show the estimated baseline and energy savings for the measures recommended in this project.

 

 

Table 3: Baseline Summary
 SYSTEMS AFFECTED BY RECOMMENDED MEASURES AVERAGE POWER (KW) OPERATING HOURS/YR ENERGY CONSUMPTION (KWH/YR)   
CHILLERS 88.6 8,400 744,042
CHILLER/PROCESS PUMPS 20.2 8,400 169,956
RECIRC PUMPS 73.5 8,400 617,508
TOTAL 182 8,400 1,531,506

 

Table 4: Savings Summary
 EEM #  SYSTEM AVERAGE POWER (KW)  OPERATING HOURS/YR  REDUCED ENERGY
CONSUMPTION (KWH/YR)
REDUCED DEMAND (KW)    ENERGY SAVINGS (KWH/YR)
1 CHILLERS, HIGHER SET POINT 88.6 2,364 209,406 88.6 534,636
NEW COOLING TOWER 6.7 6,036 40,586 6.7 (40,586)
TOTAL EEM1 SAVINGS: 95.3 494,050
2 RECIRC PUMPS 11.0 8,400 92,626 62.5 524,881
TOTAL 106.3   342,618 253.1 1,018,931

 

Conclusions

The addition of an evaporative cooler and tower-free cooling controls to a process cooling system can idle a chiller much of the year in dryer climates.  This can save over half the chiller energy.  Optimization of recirculation cooling systems can also be done saving over ¾ of pump energy.

 

For more information, please contact Tim Dugan P.E., President, Compression Engineering Corporation, tel: 503-520-0700, email:Tim.Dugan@comp-eng.com, www.comp-eng.com.

To read similar Cooling System Assessment or Plastic Industry articles, please visit coolingbestpractices.com/system-assessments/chillers or visit coolingbestpractices.com/industries/plasticsrubber.